Case Study No. 37

Case Study

Aeronautical Cleanroom

Contracted as a specialist subcontractor to design and build a Grade D Cleanroom constructed within the existing facility in isolation. The cleanroom was utilised as part of an aeronautical production line and was primarily used for the repair and painting of composite wing components for the A350.



  • Structural Frame Support.
  • 8 metres High Composite Panel System.
  • Grade D with Only 8 ac/h.
  • AHU, DX Cooling and Heating.
  • Sealed Rapid Roller Doors.
  • 500 Lighting Lux using a High Bay Lamp.
  • Fully Commissioned upon Completion.