Boulting Environmental Services Logo - BES

Slide 2 Slide 3 Slide 4

Case Study No. 31

Case Study

Cleanroom Manufacturing Facility

This new Grade C cleanroom was constructed within a live production facility. New temporary access routes had to be constructed and utilised throughout the duration of the project. The location of which was critical from the outset of design. A strict clean build protocol was adopted during construction.



  • Eradicate any Cross Contamination
  • Heavy Demolition and Excavation
  • Plasterboard for a Fully Vinyled Finish
  • New Metal Doors and Vision Panels
  • Dedicated HVAC system, with Low Level Return
  • DX Cooling and LPHW Reheat Battery
  • Inverter Driven Supply and Extract Fans