Further to our recent communication with regards the construction update for the new sterile filling facility at Bio Products Laboratory Limited (BPL), we are now delighted to report our Process Engineering activities are well underway. Working in close collaboration and partnership with BPL’s Capital Projects, Engineering, Maintenance and Validation Departments, BES’s Process Engineering Teams are currently designing and will install, commission and validate the Critical, High Purity Process Utilities comprising Purified Water, Water for Injection, Clean Steam and Compressed Air to the latest pharmacopeial regulatory standards...READ MORE
We are very pleased to report that our Southern Project Team have been recently recognised at the award ceremony at AstraZeneca’s Southern Contractors Safety forum & AZCAS.
Project engineer, James Robinson has achieved a First Class Honours degree from UCLan (University of Central Lancashire) after BES enabled him to complete both an HNC and a degree as part of his apprenticeship. James joined BES aged just 16 after completing a year at sixth form college and deciding that he wanted to earn as he learned instead of going down a more traditional academic route. Following a few weeks’ work experience with the company, he was taken on as an apprentice and, for the past six years, he has combined his role as a trainee project engineer with his studies...READ MORE
We have recently completed a £1.8 million project to create a Quality Assurance (QA) laboratory to GMP standards within an existing high bay warehouse. Delivering the project for a major pharmaceutical company, BES fulfilled the role of a principal designer and principal contractor, under CDM. The company successfully completed the 24-week project over four weeks early, equating to a programme reduction of 20%...READ MORE
Following the completion of the design phase, construction works on the syringe fill and assembly project for AstraZeneca have now begun in earnest. Fulfilling the role of Principal Contractor, our first activity is to construct a new extension to the building to house a number of new process control panels for the new filling line. The slab has now been poured and both the internal and external steelwork has been delivered ready for installation...READ MORE
We are excited to confirm that construction work for the new sterile filling facility at our site is now well under way. The expansion of our current filling capacity will include an extended, 1,000m2 suite, and will help support the increasing global need for our Plasma-Derived Medicinal Products (PDMPs), including new products currently in development at BPL...READ MORE
Works are progressing well on the construction of the new Sterile Production Plant at AstraZeneca in Macclesfield. We are very excited to report the achievement of a significant milestone, as the facility’s four Chillers, utilizing the environmentally friendly, high efficiency ammonia refrigerant, were successfully delivered and positioned. Each Chiller, weighing 17 tonnes, was lifted into position utilizing a 450 tonne crane. As Principal Contractor on this project, we are thrilled to meet this milestone with all works carried out safely and on time. A great collaborative effort by all involved!
Following a sustained increase in demand for design projects over the past financial year, BES, the specialist in delivery of complex projects for the pharmaceutical and healthcare sectors, has increased its design team with 14 new roles. The move follows a bumper year for BES, with 10 independent design commissions completed over the past 12 months, representing a combined value of £2.5 million. We also delivered a similar number of projects totalling circa £50 million, which combine design, engineering, construction and commissioning during the same period...READ MORE
BES has begun construction of a further sterile production plant for the Zoladex cancer drug at AstraZeneca’s Macclesfield campus. Officially announced during a site visit by Prime Minister Boris Johnson, the project follows BES’s successful design and construction of a sterile production facility for the manufacture of Zoladex at the site in 2016. The company has leveraged its multi-disciplinary expertise to deliver a wide variety of turnkey capital investment projects for AstraZeneca over the past 20 years, including the recent Global Packing Centre in Macclesfield...READ MORE
We are very proud to announce that BES has achieved certification for ISO 45001 Occupational Health & Safety Management Standard, aligned with our existing ISO 9001 Quality Management System; and as such we have been awarded with an integrated certificate. Introduced in March 2018, ISO 45001 is an international standard for occupational health and safety at work developed by national and international committees independent of government. It helps provide a structured framework to proactively improve safety performance, ensuring a safe and healthy workplace...READ MORE